NEW QUESTION 35
Test Tools and Automation
After a selection process you have selected a test management tool that is going be introduced in your organization and used by your test team in a pilot project.
You have already identified the member of your test team who will be the administrator of the tool, since he/she has a significant experience with the administration of test management tools and so he/she is able to make effective and efficient up-front decisions about "how" the tool will be used. You have also developed a training plan for the other members of your test team.
In collaboration with the administrator of the tool you have also devised standard ways of managing, storing and maintaining the tool and its assets including backup/restore procedures.
You have also analyzed standard formats supported by the tool (CSV, XLS, XML, etc.) to export, import and archive all the information managed by the tool itself (requirements, test case specifications, test plans etc.) for compliance with the most important test management tools, in order to minimize the impacts of migrating this information to a new tool that could replace the existing one in the future.
Which of the following phases in the lifecycle of the new tool has NOT been adequately considered in this description?
- A. Retirement
- B. Acquisition
- C. Evolution
- D. Support and maintenance
Answer: C
NEW QUESTION 36
You are a Test Manager working for a software organization where reviews have never been applied. After a meeting with your managers examining a business case for reviews, (including their costs, benefits, and potential issues), the management finally decides to adopt formal reviews for future projects.
You have been given a budget that you have spent to provide training in the review process and to introduce the review process on a pilot project.
On that pilot project the introduction of reviews has been very positive in terms of positive involvement from all the participants. All the reviews applied to different documents have been very effective for their purposes (especially at revealing defects).
Which of the following answers describes an important success factor for the introduction of formal reviews which is missing in this scenario?
K4 3 credits
- A. Definition and use of metrics to measure the ROI (Return On Investment)
- B. Participant support
- C. Training in the review process
- D. Management support
Answer: A
NEW QUESTION 37
You are working on a project to develop an authentication system for an e-commerce website. This system provides two features: Registration and authentication. Two different development teams develop these two features.
There is a high likelihood that the delivery of the authentication feature to the test team will be three weeks later. To complete the registration the user must provide the following registration inputs: Name, surname, birth date, fiscal code and he/she can select a username and a password.
A registered user can be a special user or a normal user. To be identified as a special user, he/she must also provide, during the registration process, a voucher possibly received from the IT department.
Access is granted only if a user is registered and the password is correct: In all other cases access is denied. If the registered user is a special user and the password is wrong, a special warning is shown on the system console.
You are currently performing a quality risk analysis using FMEA.
Based only on the given information, which of the following is NOT a product risk that could be identified during the quality risk analysis?
K4 3 credits
- A. The late delivery of the authentication feature to the test team causes delays in the start of test execution and this could result in a shorter test period
- B. The authentication system grants access to a normal user with a wrong password
- C. The authentication system denies access for a special user with a wrong password, but doesn't display a special warning on the system console
- D. The authentication system grants access to a special user with a wrong password
Answer: A
NEW QUESTION 38
You are following a risk-based testing strategy. The test execution time is very limited. Assume that all the product risk items require more or less the same level of test effort.
Which of the following answers describes the best execution schedule in this scenario?
Number of correct responses: 1
K3 3 credits
- A. 1- Test the correct pre-activation of the Smart Card
2- Test the correct activation of the Smart Card
3- Test the correct charge of the Smart Card with the required contents
4- Test the acceptance of transactions coming from the IVR channel - B. 1- Test the acceptance of transactions coming from the IVR channel
2- Test the correct charge of the Smart Card with the required contents
3- Test the correct pre-activation of the Smart Card
4- Test the correct activation of the Smart Card - C. 1- Test the correct activation of the Smart Card
2- Test the correct pre-activation of the Smart Card
3- Test the correct charge of the Smart Card with the required contents
4- Test the acceptance of transactions coming from the IVR channel - D. 1- Test the correct pre-activation of the Smart Card
2- Test the correct charge of the Smart Card with the required contents
3- Test the correct activation of the Smart Card
4- Test the acceptance of transactions coming from the IVR channel
Answer: A
NEW QUESTION 39
Test Management
You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:
I. Availability of re-usable test systems and documentation from previous, similar projects II. Unexpected timing of components arrival III. Stability of the integration test team (no turnover) IV. Many and geographically distributed sub-teams Which of the following statements is true?
- A. II. and III. can negatively affect the estimation
- B. II. and IV. can negatively affect the estimation
- C. III. and IV. usually favor the accuracy of the estimation effort
- D. I.and II. can negatively affect the estimation III. and IV. usually favor the accuracy of the estimation effort
- E. III. and IV. can negatively affect the estimation
- F. I.and II. usually favor the accuracy of the estimation effort
- G. II. and III. usually favor the accuracy of the estimation effort
Answer: C
Explanation:
Section: Test Management
NEW QUESTION 40
You are using this skills assessment spreadsheet in order to define a training development plan for your test team.
Your objective is to fill the skill gaps by having at least a team member rated as an expert for each skill identified for the "technical expertise" and "testing skills" sections, and with the ability to train the other team members.
Considering the budget constraints you can send only one person to a training course.
Based only on the given information, which of the following answers would you expect to be the best option to achieve your objective?
- A. Send Robert to a performance testing training course
- B. Send Mark to a test automation training course
- C. Send John to a performance testing training course
- D. Send Alex to a performance testing training course
Answer: D
NEW QUESTION 41
Testing Process
Which of the following is an example of the test closure activity indicated as "lessons learned"?
Number of correct responses: 1
K2 1 credit
- A. Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for maintenance testing
- B. Deliver a list of the open defects of a software product released into production to the service desk team
- C. Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects
- D. Archive all the test results of the acceptance testing phase
Answer: C
NEW QUESTION 42
Test Management
You are managing the system testing for a SOA based system. The integrated system consists of several subsystems:
- a SOA middleware
- a CRM (Customer Relationship Management) system
- a BRM (Billing and Revenue Management) system
- a SMS (Subscriber Management System) system
and you performed a risk analysis based on these subsystems.
At the end of the scheduled period for test execution you produce a first classical report based on the traditional metrics of testing. Test pass/fail status and bug status (open/resolved) That table provides you a distorted picture of the quality risk, because there is no indication of the risk level of the failed tests, the tests not run, or the open bugs. Thus, you produce the following table to solve this distortion issue:
In the table above, where you have introduced the concept of risk weighting, the highest risk test or bug report has a score of 1, while the lowest risk test or bug report has a score of 0.04.
Which of the following subsystems, based on the risk scores of the table, is most risky?
- A. SMS
- B. BRM
- C. SOA
- D. CRM
Answer: D
Explanation:
Section: Test Management
Explanation/Reference:
NEW QUESTION 43
An agile development team decides to hire a tester who has always workeD.
-
in independent test teams, reporting the problems found in a defect tracking system
-
in safety-critical projects, with a stronger focus on the quality of the product than on time and budget.
This agile team is focused on short-term goals to get the product released on time and within budget.
Which of the following answers would you expect to be most likely true in this scenario?
K2 1 credit
- A. The developers will immediately follow the guidelines described by the tester
- B. The tester's mission could be to verify adherence to requirements, instead of reporting formally the problems in a defect tracking system
- C. The tester can continue to report the problems found in a defect tracking system and be more focused on the quality than on time and budget constraints
- D. Agile teams like the presence of a tester in their teams and the tester will be able to adapt to the new context without any issue
Answer: B
NEW QUESTION 44
Testing Process
Which of the following statements describing the consequences of specifying test conditions at a detailed level is NOT true?
Number of correct responses: 1
K2 1 credit
- A. For system testing, the specification of test conditions at a detailed level, carried out early in the project as soon as the test basis is established, can contribute to defect prevention
- B. The specification of test conditions at a detailed level can be effective when no formal requirements or other development work products are available
- C. The specification of test conditions at a detailed level can require the implementation of an adequate level of formality across the team
- D. In an environment where the test basis is continuously changing, it is recommended to specify test conditions at a detailed level in order to achieve a better maintainability
Answer: D
NEW QUESTION 45
You are following a risk-based testing strategy. The test execution time is very limited. Assume that all the product risk items require more or less the same level of test effort.
Which of the following answers describes the best execution schedule in this scenario?
- A. 1- Test the correct pre-activation of the Smart Card
2- Test the correct activation of the Smart Card
3- Test the correct charge of the Smart Card with the required contents
4- Test the acceptance of transactions coming from the IVR channel - B. 1- Test the acceptance of transactions coming from the IVR channel
2- Test the correct charge of the Smart Card with the required contents
3- Test the correct pre-activation of the Smart Card
4- Test the correct activation of the Smart Card - C. 1- Test the correct activation of the Smart Card
2- Test the correct pre-activation of the Smart Card
3- Test the correct charge of the Smart Card with the required contents
4- Test the acceptance of transactions coming from the IVR channel - D. 1- Test the correct pre-activation of the Smart Card
2- Test the correct charge of the Smart Card with the required contents
3- Test the correct activation of the Smart Card
4- Test the acceptance of transactions coming from the IVR channel
Answer: A
Explanation:
Section: Testing Process
NEW QUESTION 46
Test Management
Which of the following statements describing how identified product quality risks should be mitigated and managed, is true?
- A. The identification of new risks, the re-assessment of the level of existing risks and the evaluation of the effectiveness of risk mitigation activities should only occur at the very beginning of a project
- B. The priority of the development and execution of tests should not be based on the risk level but only on the likelihood
- C. Risk mitigation of product quality risks can be effective only after starting test execution
- D. The extent of re-testing and regression testing activities should be based on the risk level
Answer: D
Explanation:
Section: Test Management
NEW QUESTION 47
Assume that no additional product risks have been identified during the first week of test execution.

Which of the following answers would you expect to best describe the residual risks associated with the identified product risks, at the end of the first week of test execution?
- A. The residual risk level can't be determined, because it requires that all the test cases have been executed
- B. Since R3 is the only risk for which all test cases have passed, the risk has been reduced by 20%
- C. The test execution status table indicates that the risk has been reduced by 56%
- D. The test execution table doesn't give an indication of the risk level of the open defects and the test cases that failed or are not run yet
Answer: D
Explanation:
Section: Testing Process
NEW QUESTION 48
Test Tools and Automation
Assume you are the Test Manager in charge of independent testing for avionics applications.
You are in charge of testing for a project to implement three different CSCI (Computer Software Configuration Item):
- a BOOT-X CSCI that must be certified at level B of the DO-178B standard
- a DIAG-X CSCI that must be certified at level C of the DO-178B standard
- a DRIV-X CSCI that must be certified at level A of the DO-178B standard These are three different software modules written in C language to run on a specific hardware platform.
You have been asked to select a single code coverage tool to perform the mandatory code coverage measurements, in order to meet the structural coverage criteria prescribed by the DO-178B standard. This tool must be qualified as a verification tool under DO-178B.
Since there are significant budget constraints to purchase this tool, you are evaluating an open-source tool that is able to provide different types of code coverage. This tool meets perfectly your technical needs in terms of the programming language and the specific hardware platform (it supports also the specific C-compiler).
The source code of the tool is available.
Your team could easily customize the tool to meet the project needs. This tool is not qualified as a verification tool under the DO-178B.
Which of the following are the three main concerns related to that open-source tool selection?
Number of correct responses: 3
K4 3 credits (2 credits out of 3 credits correct, 1 credit point)
- A. Is the licensing scheme of the tool compatible with the confidentiality needs of the avionics company?
- B. Is the installation procedure of the tool easy?
- C. Does the tool require a system with more than 4GB of RAM memory?
- D. Does the tool have a good general usability?
- E. Does the tool support all the types of code coverage required from the three levels A, B, C of the DO-178B standard?
- F. What are the costs to qualify the tool as a verification tool under the DO-178B?
Answer: A,E,F
NEW QUESTION 49
People Skills - Team Composition
Consider the following analysis of testing skills performed on four people: Alex, Robert, John and Mark (all the skills have been rated on an ascending scale: The higher the score, the better the skill):
Which of these people, based on this analysis, would you expect to be most suitable to work specifically as test designer?
Number of correct responses: 1
K4 3 credits
- A. Mark
- B. John
- C. Roberta
- D. Alex
Answer: C
NEW QUESTION 50
Test Management
Which of the following statements describing how identified product quality risks should be mitigated and managed, is true?
- A. The identification of new risks, the re-assessment of the level of existing risks and the evaluation of the effectiveness of risk mitigation activities should only occur at the very beginning of a project
- B. The priority of the development and execution of tests should not be based on the risk level but only on the likelihood
- C. Risk mitigation of product quality risks can be effective only after starting test execution
- D. The extent of re-testing and regression testing activities should be based on the risk level
Answer: D
NEW QUESTION 51
Testing Process
Consider an information system of a Pay-Tv company based on a SOA architecture.
The integrated system currently consists of three core systems:
- a CRM (Customer Relationship Management) system
- a BRM (Billing and Revenue Management) system
- a CAS (Conditional Access System) system
all of them communicating with SOA Middleware.
You have been asked to manage the testing activities for the integration of two additional off-the-shelf systems from two different vendors: a SMS (Short Message Service) server and an IVR (Interactive Voice Response) system.
Assume that there is a high likelihood that the two off-the-shelf systems will be low-quality and that you have a clear proof that the testing performed by the two vendors on their systems has been unsystematic and unprofessional. This obviously leads to higher quality risk for the overall integrated system.
You are the Test Manager of this project. Your main goal is to plan for testing activities to mitigate this risk.
Which of the following answers best describes the test activities (assuming it is possible to perform all of them) you should plan for?
Number of correct responses: 1
K4 3 credits
- A. You should plan for an informal and minimal acceptance test of the two off-the-shelf systems and then a single end-to-end test of the overall integrated system
- B. You should plan for two levels: a system integration test and an end-to-end test of the overall integrated system
- C. You should directly plan for a single end-to-end test focused on end-to-end tests of the overall integrated system without an acceptance test of the two off-the-shelf systems
- D. You should plan for adequate re-testing of both the systems followed by a system integration test and an end-to-end test of the overall integrated system
Answer: D
NEW QUESTION 52
Which of the following statements best describes an appropriate approach for managing exploratory testing?
Number of correct responses: 1
K2 1 credit
- A. Exploratory testing should not be managed because such testing is inherently unmanageable and not measurable
- B. Define very detailed mission statements, which allow testing work to be broken into sessions of up to 10 minutes duration in which testing is guided by these mission statements
- C. Define very generic charters to drive exploratory testing sessions of 2 days where testers are completely free to decide what to test
- D. Break the testing work in 30 to 120 minutes sessions and use properly defined mission statements consisting of two or three sentences to guide testing during these sessions
Answer: D
NEW QUESTION 53
You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:
I. Availability of re-usable test systems and documentation from previous, similar projects
II. Unexpected timing of components arrival
III. Stability of the integration test team (no turnover)
IV. Many and geographically distributed sub-teams Which of the following statements is true?
K2 1 credit
- A. II. and III. can negatively affect the estimation
- B. II. and IV. can negatively affect the estimation
- C. and III. usually favor the accuracy of the estimation effort
- D. and IV. usually favor the accuracy of the estimation effort
- E. and II. usually favor the accuracy of the estimation effort
- F. I. and II. can negatively affect the estimation III. and IV. usually favor the accuracy of the estimation effort
- G. III. and IV. can negatively affect the estimation
Answer: D
NEW QUESTION 54
The following are the exit criteria described in the test plan of a software product:
EX1. The test suite for the product must ensure that at least each quality risk item is covered by at least one test case (a quality risk item can be covered by more test cases).
EX2. All test cases in the test suite must be run during the execution phase.
EX3. Defects are classified into two categories: "C" (critical defect) and "NC" (non-critical defect). No known C defects shall exist in the product at the end of the test execution phase.
Which of the following information is useless when the specified exit criteria is evaluated?
K2 1 credit
- A. A chart, showing the trend in the lag time from defect reporting to resolution, extracted from the defect tracking system
- B. A list of all the open defects with the associated classification information extracted from the defect tracking system
- C. The execution status of all the test cases extracted from the test management tool
- D. A traceability matrix showing the relationships between the product risk items and the test cases
Answer: A
NEW QUESTION 55
Reviews
You are the Test Manager of a project that adopts a V-model with four formal levels of testing: unit, integration, system and acceptance testing.
On this project reviews have been conducted for each development phase prior to testing, which is to say that reviews of requirements, functional specification, high-level design, low-level design and code have been performed prior to testing.
Assume that no requirements defects have been reported after the release of the product.
Which TWO of the following metrics do you need in order to evaluate the requirements reviews in terms of phase containment effectiveness?
- A. Total number of defects attributable to requirements found during unit, integration, system and acceptance testing
- B. Total number of defects found during functional specification review, high-level design review, low-level design review, code review, unit testing, integration testing, system testing and acceptance testing
- C. Number of defects found during the requirements review
- D. Total number of defects attributable to requirements, found during functional specification review, high- level design review, low-level design review, code review, unit testing, integration testing, system testing and acceptance testing
- E. Time to conduct the requirements review
Answer: C,D
NEW QUESTION 56
Improving the Testing Process
Which of the following statements about the STEP test process improvement model is true?
Number of correct responses: 1
K2 1 credit
- A. The STEP model stresses defect detection and demonstration of capability, whereas the defect prevention is a secondary potential goal of testing
- B. In the STEP model, testware design occurs after coding
- C. The STEP model assures that the system requirements specification and the test design specification processes don't overlap
- D. In the STEP model, tests validate the requirements and use cases when they are developed
Answer: D
NEW QUESTION 57
......
ISQI CTAL-TM_Syll2012 Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
ISQI Certifications Free Certification Exam Material from PDFVCE with 66 Questions: https://topexamcollection.pdfvce.com/ISQI/CTAL-TM_Syll2012-exam-pdf-dumps.html